A. INTRODUCTION:
A.1 Calibration data for specific
system
A.2 Summary Helium Transfer
Procedure
A.3 Suggested data recording
1.
SYSTEM EVACUATION AND COOLDOWN
1.1 Checking Vacuum
1.2 Pumping on the SRM
Vacuum
1.3 Pumping on the Helium
Reservoir
1.4 Leak Testing
1.5 Cool Down with Cryocooler
Precool
1.6 Cool Down with Helium
Transfer and Cryocooler
2.
LIQUID HELIUM REFILLS
2.1 Preparation
2.2 Begin Transfer
2.3 Stop Transfer
2.4 Using a Second Supply
Dewar
2.5 Concluding the Transfer
3.
INSTRUMENTATION
3.1 Helium Level Gauges
3.2 Thermometers
3.3 Heaters
3.4 Field Nulling Coils
3.5 Switching the Superconducting
Shield
4.
PLUGS IN FILL, VENT OR SAFETY
4.1 Air Plug in Fill Line
4.2 Air Plug in the Vent
Line
4.3 Pumping on the Plugged
Line to Clear
4.4 Clearing a Plug by
Alternately Pumping and Pressurizing a Line
4.5 Venting the SRM Through
the Fill Port When the Vent Port is Plugged
5.
CRYOCOOLER MAINTENANCE AND PROBLEMS
5.1 Replacement of the
adsorber
5.2 Cold head sticking
noises
5.3 Cold head replacement
6. HAZARDS
OF SYSTEM EXPLOSION
7. TELEPHONE,
E-MAIL AND FAX CONTACTS FOR 2G ENTERPRISES
|